Filters
Question type

Study Flashcards

 A merge occurs when one node precedes multiple nodes.

A) True
B) False

Correct Answer

verifed

verified

 Milestones are easy to achieve and are always achieved through one main activity.

A) True
B) False

Correct Answer

verifed

verified

 Which document is most likely to include planned project start and end dates which serve as the starting points for a detailed schedule?


A) resource breakdown structure
B) milestones list
C) organizational process assets update
D) project charter

E) All of the above
F) B) and D)

Correct Answer

verifed

verified

 In project schedule management, the ultimate goal of which process is to provide a basis for monitoring project progress for the time dimension of the project?


A) defining activities
B) sequencing activities
C) developing a schedule
D) estimating activity resources

E) A) and D)
F) A) and C)

Correct Answer

verifed

verified

 Duration estimates can be provided as a discrete number, a range, or as a(n) _____.

Correct Answer

verifed

verified

three-poin...

View Answer

 _____ involves the processes required to ensure timely completion of a project.

Correct Answer

verifed

verified

Project sc...

View Answer

 To define activities, the project team should start with reviewing the schedule management plan, scope baseline, enterprise environmental factors, and organizational processes.

A) True
B) False

Correct Answer

verifed

verified

 Where would a draft schedule for a project most likely be found?


A) project buffer
B) project charter
C) resource breakdown structure
D) project's dummy activities list

E) A) and D)
F) A) and B)

Correct Answer

verifed

verified

 During which relationship is the "from" activity unable start until the "to" activity is started?


A) start-to-start
B) finish-to-finish
C) finish-to-start
D) start-to-finish

E) B) and D)
F) A) and B)

Correct Answer

verifed

verified

 In a critical path analysis, the shortest path is what drives the completion date for the project.

A) True
B) False

Correct Answer

verifed

verified

 A white diamond on a Tracking Gantt chart represents a(n) _____.

Correct Answer

verifed

verified

 In a network diagram, it is mandatory for every item on the WBS to be shown instead of only those activities with dependencies.

A) True
B) False

Correct Answer

verifed

verified

 Which is true of dummy activities?


A) They have long durations.
B) They show logical relationships between activities.
C) They have a large range of resources.
D) They have limited time periods.

E) All of the above
F) A) and B)

Correct Answer

verifed

verified

 Which technique is used for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost?


A) dependency
B) crashing
C) critical chain scheduling
D) feeding buffers

E) None of the above
F) A) and B)

Correct Answer

verifed

verified

 SMART criteria are guidelines suggesting that milestones should be _____.

Correct Answer

verifed

verified

Specific, Measurable...

View Answer

 Project schedules grow out of basic documents such as the project charter.

A) True
B) False

Correct Answer

verifed

verified

 What is the Theory of Constraints? Describe critical chain scheduling, an application of the Theory of Constraints.

Correct Answer

verifed

verified

The Theory of Constraints (TOC) is a man...

View Answer

 Critical chain scheduling assumes that resources multitask and maximizes multitasking.

A) True
B) False

Correct Answer

verifed

verified

 In project schedule management, the primary output of defining activities is a schedule management plan.

A) True
B) False

Correct Answer

verifed

verified

 Which statement best describes the difference between an activity list and an activity attribute?


A) As opposed to an activity attribute, an activity list provides resource requirements and constraints related to activities.
B) An activity list provides a more concrete list of milestones for a project than an activity attribute.
C) An activity attribute is a tabulation of activities to be included on a project schedule whereas an activity list is not.
D) An activity attribute provides more schedule-related information about each activity than an activity list.

E) All of the above
F) None of the above

Correct Answer

verifed

verified

Showing 61 - 80 of 99

Related Exams

Show Answer